November 16, 2023 – The paving of all of the roads noted below have been completed. Line painting will be done in 2024.
October 11, 2023 - Weather permitting, all roads noted below should be completed by October 14th. In the event of equipment failure or inclement weather, work will continue Monday, October 16th until completed. Shouldering operations will commence shortly after paving; however, the new asphalt will need to sit for a week or so before we start that operation. The shouldering operation will take an approximate 2 to 3 days.
- Marionville Road – Base lift has been completed. A second 40mm lift will be added starting Thursday, October 12th and paving completed by Friday, October 13th.
- Bisson Road – Paving scheduled to be completed by end of day, Wednesday, October 11th.
- Forest Hill Road - Scheduled to be paved by end of day Saturday, October 14th.
October 5, 2023 - The paving of Beach Street in Winchester has been completed. Marionville Road and Bisson Road are scheduled next to be paved and work will begin in the coming days. Traffic control measures will be in effect as required and no significant impact to traffic flow is anticipated.
August 22, 2023 - The list of roads for asphalt paving in 2023 includes Marionville Road, Bisson Road, Forest Hill Road and Beach Street, as detailed below. Pulverizing of these roads will commence on Sept. 28th.
- Marionville Rd., Winchester – 2450m
- Bisson Rd., Winchester – 1500m
- Forest Hill Rd., Winchester – 600m
- Beach St., Winchester – 140m