November 22nd, 2023 Update: The South Nation Bridge reconstruction project is now complete. We thank all travellers for their understanding and patience during this project.
November 8th, 2023 Update: The bridge rehabilitation work is scheduled to be completed November 16th. The $2.16M project was funded by the Canada Community-Building Fund from AMO.
October 2023 Update: The bridge rehabilitation work is progressing well, with the top-side work anticipated to be done and to have the road re-opened by mid-November. The full completion of the project is scheduled to be done by the end of November.
May 9th, 2023 -- The South Nation Bridge, located on SDG 43 between South Street West and Chesterville Queen Street in Chesterville will undergo a significant rehabilitation this year. The Counties SDG will be sharing more information on this project in the coming weeks. Beginning May 23rd and lasting until October, SDG 43 access to the bridge will be closed. Motorists will have to use the alternate route outlined below. Westbound traffic will be detoured off of SDG 43 and down SDG 7 through the village, continuing northbound until SDG 9 to take traffic westbound again to reconnect with SDG 43. The contractor will work diligently to ensure this project is completed as efficiently and quickly as possible. We apologize for this disruption.
Add new comment